Calculating Process Times

Optimize your machine utilization by individually calculating process times for CAM runs on all process levels:

  • Level 1: on the machining level
  • Level 2: on the programming level (sum of type 1 per NCNUM)
  • Level 3: on the station level (sum of type 2 per machine/station)
  • Level 4: on the parts level (sum of type 3 per part)

To do this, save the ‘Additional time value’ as a formula or simple value in the time calculation category within the category Machining Properties>Time Calculation in a Machining principle. In the field ‘Add time value: description’, you can add a description, if desired, so that the time value can be associated with the machining within the database.

The results of the process time calculation can be found in the view table IDBPROTIMECALC.